Project Description:
DISTRICT 6- SCHEDULED & EMERGENCY GUARDRAIL REFURBISHMENT AT VARIOUS LOCATIONS
Work will be assigned, as needed, throughout the life of the contract.
Location:
  • City of Boston
  • Design Responsibility: In-House Boston
    Project Manager: John Gendall
    Estimated Total Contract Cost: $457,427.61
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 07/10/2010 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/25/2010
    Project Initiation Form PIF Entered 03/08/2010
    Project Initiation Form PRC Submitted 03/09/2010
    Project Review Committee PRC Approved 05/13/2010
    Project Review Committee Letter 05/24/2010
    Project Status Advertised 07/10/2010
    Project Management
    Final Design PS&E Received 06/10/2010
    Final Design PS&E to FAPRO 06/09/2010