Project Description:
DISTRICT 6- SCHEDULED & EMERGENCY STRUCTURAL & SUBSTRUCTURE REPAIRS AT VARIOUS LOCATIONS
Work will be assigned, as needed, throughout the life of the contract.
Location:
Resident Engineer: Gene Lee
Construction Bid Price: $6,354,233.00
Initial Construction Estimate: $6,926,345.00
District: District 6

Contracts (1) Progress
# 88710 -- Construction Contract
Scheduled and Emergency Bridge Structure and Substructure Repairs at Various Locations (Re-Advertised Project). Completed

Bridges

Contract Dates
Notice to Proceed: 12/09/2015
Contract Information
Project Designer: In-House Boston
Funding Source: Non Federal Aid
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 02/25/2010
Project Initiation Form PIF Entered 03/08/2010
Project Initiation Form PRC Submitted 03/09/2010
Project Review Committee PRC Approved 05/13/2010
Project Review Committee Letter 05/24/2010
Project Status Advertised 08/30/2014
Project Status Advertised 06/27/2015
Project Management
100% Design 100% Package Received 07/18/2014
Final Design PS&E Received 08/15/2014
Final Design PS&E Received 04/09/2015
Final Design PS&E to FAPRO 08/27/2014
Final Design PS&E to FAPRO 05/08/2015