DISTRICT 6- TREE TRIMMING & SITE DISTANCE IMPROVEMENT AT VARIOUS LOCATIONS
Work will be assigned, as needed, throughout the life of the contract.
Location:
Resident Engineer: Eugene Messom
Construction Contract Value: $195,729.50
Construction Bid Price: $162,437.50
Initial Construction Estimate: $275,250.00
District: District 6

Contracts (1) Progress
# 66675 -- Construction Contract
Tree Removal and Site Distance Clearing at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/05/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/25/2010
    Project Initiation Form PIF Entered 03/08/2010
    Project Initiation Form PRC Submitted 03/09/2010
    Project Review Committee PRC Approved 05/13/2010
    Project Review Committee Letter 05/24/2010
    Project Status Advertised 08/14/2010
    Project Management
    Final Design PS&E Received 08/09/2010