Project Description:
SUTTON- INTERSECTION IMPROVEMENTS @ ROUTE 146 & BOSTON ROAD
The project consists of resurfacing and box widening, along with geometric modifications to provide an additional through lane in each direction on Route 146, as well as additional turning lanes on both Route 146 and Boston Road. Additional work includes upgraded traffic signal equipment at the intersection and construction of retaining walls. The project extends from approximately 1600 feet north of Boston Road to approximately 2600 feet south of Boston Road.
Location:
  • Town of Sutton
  • Resident Engineer: Stephen Shamoian
    Construction Contract Value: $7,391,939.85
    Construction Bid Price: $5,556,375.81
    Initial Construction Estimate: $5,985,260.50
    District: District 3

    Contracts (4) Progress
    # 58213 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64326 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77233 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals) along a Section of Route 146 (Worcester-Providence Turnpike) and Boston Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/18/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/03/2010
    Project Initiation Form PIF Entered 03/03/2010
    Project Initiation Form PRC Submitted 04/14/2010
    Project Review Committee PRC Approved 05/13/2010
    Project Review Committee Letter 06/03/2010
    Project Status Advertised 04/13/2013
    Project Management
    100% Design 100% Package Received 02/06/2012
    100% Design 100% Package Comments to DE 04/23/2012
    25% Design 25% Package Received 11/12/2010
    25% Design 25% Package Comments to DE 03/01/2011
    25% Design Design Public Hearing 07/28/2011
    75% Design 75% Package Received 02/06/2012
    75% Design 75% Package Comments to DE 04/23/2012
    Final Design PS&E Received 12/10/2012
    Final Design PS&E Received 03/11/2013
    Final Design PS&E to FAPRO 04/10/2013