Project Description:
BOSTON- TRAFFIC SIGNAL IMPROVEMENTS AT 9 LOCATIONS
The purpose of this projects is to upgrade five (5) traffic control signals and install four (4) new signals (a total of 9 locations). Existing devices are outdated and require additional functionality to meet MUTCD standards. Some traffic signals will include communication cable and field equipment (local controllers, detectors, etc). Certain locations will be connected to the Boston Transportation Department central traffic computer system, which will allow remote monitoring and real time adjustments to timing. Sidewalk ramps will be reconstructed as needed in order to meet current AAB standards. All signals will be retimed based on current traffic volumes. Certain locations require minor geometric changes to improve safety and operations. The locations are Arlington Street at Beacon and Embankment Road; Arlington at Marlborough; Cambridge at Harvard and Franklin; Cambridge at Windom; Pleasant at Savin Hill; Waltham at Washington; Dudley at Shirley; Cummins Highway at Rockdale; and Washington at West Concord.
Location:
  • City of Boston
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Scott Leisey
    Construction Bid Price: $3,187,389.92
    District: District 6

    Contracts (1) Progress
    # 97589 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at 9 Intersections. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/02/2017
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/18/2010
    Project Initiation Form PIF Entered 04/21/2010
    Project Initiation Form PRC Submitted 04/28/2010
    Project Review Committee PRC Approved 05/13/2010
    Project Review Committee Letter 06/08/2010
    Project Status Advertised 08/27/2016
    Project Management
    100% Design 100% Package Received 06/06/2016
    100% Design 100% Package Comments to DE 07/12/2016
    25% Design 25% Package Received 06/24/2011
    25% Design 25% Package Received 08/01/2011
    25% Design Design Public Hearing 05/23/2013
    25% Design Design Public Hearing 05/29/2013
    25% Design Design Public Hearing 06/20/2013
    75% Design 75% Package Received 01/08/2014
    75% Design 75% Package Comments to DE 03/31/2016
    Final Design PS&E Received 08/19/2016
    Final Design PS&E to FAPRO 08/22/2016