Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NEW BEDFORD- RECONSTRUCTION OF ROUTE 18 (JFK HIGHWAY), FROM COVE STREET TO GRIFFIN COURT (PHASE II)
Work on the reconstruction of Route 18 project consists of roadway resurfacing and reconstruction, traffic signal installation, sidewalk and bike path installation on a section of Route 18 (JFK Highway) south of the downtown section ending at Cove Street. New signs and pavement markings are included in the .95 mile long project.
Location:
  • City of New Bedford
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Scott Borges
    Construction Bid Price: $9,157,334.25
    District: District 5

    Contracts (1) Progress
    # 97599 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 18 (JFK Memorial Highway) (Phase II). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/16/2017
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/24/2010
    Project Initiation Form PIF Entered 03/24/2010
    Project Initiation Form PRC Submitted 04/30/2010
    Project Review Committee PRC Approved 01/11/1999
    Project Status Advertised 08/27/2016
    Project Management
    100% Design 100% Package Received 07/08/2016
    100% Design 100% Package Comments to DE 08/05/2016
    25% Design 25% Package Received 07/31/2012
    25% Design 25% Package Received 04/23/2014
    25% Design 25% Package Received 09/23/2014
    25% Design 25% Package Comments to DE 05/30/2013
    25% Design 25% Package Comments to DE 08/01/2014
    25% Design 25% Package Comments to DE 04/21/2015
    25% Design Design Public Hearing 07/14/2015
    25% Design Design Public Hearing 10/29/2015
    75% Design 75% Package Received 12/30/2015
    75% Design 75% Package Comments to DE 03/25/2016
    Final Design PS&E Received 08/17/2016
    Final Design PS&E to Peer Reviewer 08/03/2016
    Final Design Peer Review Comments to DE 08/19/2016
    Final Design PS&E to FAPRO 08/22/2016