Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
UPTON- RECONSTRUCTION OF HIGH STREET AND HOPKINTON ROAD (PHASE I)
The proposed work includes roadway rehabilitation of High Street and Hopkinton Road, from 500 feet west of the intersection of School Street and Westboro Road to the Hopkinton Town line. Additional work includes signalization of and minor geometric improvements to the School Street and Westboro Road intersection, construction of proposed retaining walls, drainage improvements, guard rail installation, granite edging and related work.
Location:
  • Town of Upton
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Christopher Lee
    Construction Bid Price: $5,097,608.00
    District: District 3

    Contracts (1) Progress
    # 109186 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Hopkinton Road and High Street (Phase 1) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/05/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/05/2010
    Project Initiation Form PIF Entered 04/05/2010
    Project Initiation Form PRC Submitted 08/08/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Status Advertised 08/03/2019
    Project Management
    100% Design 100% Package Received 12/17/2018
    100% Design 100% Package Comments to DE 02/04/2019
    25% Design 25% Package Received 05/08/2012
    25% Design 25% Package Comments to DE 11/08/2012
    25% Design Design Public Hearing 10/22/2015
    75% Design 75% Package Received 08/18/2016
    75% Design 75% Package Comments to DE 12/19/2016
    Final Design PS&E Received 06/21/2019
    Final Design PS&E to FAPRO 07/22/2019