Project Description:
MONTAGUE- RESURFACING & RELATED WORK ON GREENFIELD ROAD, FROM TURNERS FALLS ROAD TO THE FUTURE BIKE/PED BRIDGE OVER THE B&M RAILROAD (1.75 MILES)
The project will rehabilitate the town-owned segment of Greenfield Road south of the B&M railroad in Montague, from the railroad to Turners Falls Road, for a total length of 1.73 miles. With the demolition of the Greenfield Road Bridge over the B&M railroad the northern 0.4 miles of the road is functionally a dead end. The resurfacing of Greenfield Road is required to fulfill an agreement made with the municipality when the decision to permanently remove the bridge was established. Roadway improvements will include drainage system repairs/upgrades and related work. Under a separate project, a pedestrian bridge is proposed to be constructed at the former highway bridge site to provide a link for bicycles and pedestrians with the rest of Greenfield Road to the north.
Location:
  • Town of Montague
  • Resident Engineer: Daniel Boucher
    Construction Contract Value: $1,227,587.00
    Construction Bid Price: $879,293.50
    Initial Construction Estimate: $828,172.25
    District: District 2

    Contracts (1) Progress
    # 80147 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Greenfield Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/20/2014
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/08/2010
    Project Initiation Form PIF Entered 04/08/2010
    Project Initiation Form PRC Submitted 04/12/2010
    Project Review Committee PRC Approved 05/13/2010
    Project Review Committee Letter 06/08/2010
    Project Status Advertised 10/05/2013
    Project Management
    100% Design 100% Package Received 03/22/2013
    100% Design 100% Package Comments to DE 05/07/2013
    25% Design 25% Package Received 12/14/2012
    25% Design 25% Package Comments to DE 02/27/2013
    75% Design 75% Package Received 03/22/2013
    Final Design PS&E Received 07/17/2013
    Final Design PS&E Received 09/19/2013
    Final Design PS&E to FAPRO 08/28/2013
    Final Design PS&E to FAPRO 09/24/2013