Project Description:
NORWOOD- INTERSECTION IMPROVEMENTS AT ROUTE 1A & UPLAND ROAD/WASHINGTON STREET & PROSPECT STREET/FULTON STREET
Work on this project includes traffic signal installation and associated geometric improvements at the intersection of Route 1A (Upland Road/Washington Street), Prospect Street and Fulton Street in Norwood.
Location:
  • Town of Norwood
  • Construction Begins: Autumn 2023
    Resident Engineer: Charles Young
    Construction Bid Price: $8,909,225.40
    District: District 5

    Contracts (3) Progress
    # 123868 -- Construction Contract
    Intersection Improvements at Route 1A & Upland Road/Washington Street & Prospect Street/Fulton Street 2% Complete
    # 64312 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/14/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/16/2010
    Project Initiation Form PIF Entered 06/23/2010
    Project Initiation Form PRC Submitted 07/21/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Status Advertised 08/26/2023
    Project Management
    100% Design 100% Package Received 04/28/2022
    100% Design 100% Package Received 05/09/2022
    100% Design 100% Package Comments to DE 07/06/2022
    25% Design 25% Package Received 04/18/2012
    25% Design 25% Package Comments to DE 10/24/2014
    25% Design Design Public Hearing 02/25/2015
    75% Design 75% Package Received 10/10/2019
    75% Design 75% Package Comments to DE 01/08/2020
    75% Design 75% Package Received - Resub 1 12/08/2021
    Final Design PS&E Received 11/15/2022
    Final Design PS&E to FAPRO 08/07/2023
    Final Design PS&E Received - Resub 1 05/25/2023