Project Description:
NORWOOD- INTERSECTION IMPROVEMENTS AT ROUTE 1A & UPLAND ROAD/WASHINGTON STREET & PROSPECT STREET/FULTON STREET
Work on this project includes traffic signal installation and associated geometric improvements at the intersection of Route 1A (Upland Road/Washington Street), Prospect Street and Fulton Street in Norwood.
Location:
  • Town of Norwood
  • Construction Begins: Autumn 2023
    Resident Engineer: Charles Young
    Construction Bid Price: $8,909,225.40
    District: District 5
    Current Status: Milling and paving Fulton /Prospect and RT 1A Installing Granite Curbing on RT 1A Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 11/14/2024)

    Contracts (3) Progress
    # 123868 -- Construction Contract
    Intersection Improvements at Route 1A & Upland Road/Washington Street & Prospect Street/Fulton Street 15% Complete
    # 64312 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/14/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Milling and paving Fulton /Prospect and RT 1A Installing Granite Curbing on RT 1A Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/16/2010
    Project Initiation Form PIF Entered 06/23/2010
    Project Initiation Form PRC Submitted 07/21/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Status Advertised 08/26/2023
    Project Management
    100% Design 100% Package Received 04/28/2022
    100% Design 100% Package Received 05/09/2022
    100% Design 100% Package Comments to DE 07/06/2022
    25% Design 25% Package Received 04/18/2012
    25% Design 25% Package Comments to DE 10/24/2014
    25% Design Design Public Hearing 02/25/2015
    75% Design 75% Package Received 10/10/2019
    75% Design 75% Package Comments to DE 01/08/2020
    75% Design 75% Package Received - Resub 1 12/08/2021
    Final Design PS&E Received 11/15/2022
    Final Design PS&E to FAPRO 08/07/2023
    Final Design PS&E Received - Resub 1 05/25/2023