SANDWICH- INTERSECTION (ROUNDABOUT) IMPROVEMENTS @ COTUIT ROAD/HARLOW ROAD/SOUTH SANDWICH ROAD
The proposed work includes the construction of a modern roundabout at the intersection of Cotuit Road and Harlow Road/South Sandwich Road in Sandwich. The intersection of Asa Meiggs Road and Cotuit Road will be reconfigured to a right angle. The profile will be reduced to improve visibility. The project will also include minor drainage improvements, signs and pavement markings.
Location:
  • Town of Sandwich
  • Resident Engineer: Michael McGovern
    Construction Contract Value: $1,050,627.00
    Construction Bid Price: $898,026.90
    Initial Construction Estimate: $980,004.00
    District: District 5

    Contracts (3) Progress
    # 57791 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to the MassHighway on an open end basis located in the Cape Cod Commission region. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70930 -- Construction Contract
    Construction of a Roundabout at the Intersection of Cotuit, Harlow, and South Sandwich Roads. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/17/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/16/2010
    Project Initiation Form PIF Entered 04/16/2010
    Project Initiation Form PRC Submitted 05/17/2010
    Project Review Committee PRC Approved 05/13/2010
    Project Review Committee Letter 06/09/2010
    Project Status Advertised 09/03/2011
    Project Management
    100% Design 100% Package Received 08/15/2011
    25% Design 25% Package Received 05/13/2010
    25% Design 25% Package Comments to DE 10/26/2010
    25% Design 25% Package Approved 01/14/2011
    25% Design Design Public Hearing 03/01/2011
    75% Design 75% Package Received 05/10/2011
    75% Design 75% Package Comments to DE 06/23/2011
    Final Design PS&E Received 08/15/2011
    Final Design PS&E to FAPRO 08/31/2011
    Consultant Contract Process Scope to DE 04/30/2009
    Consultant Contract Process NTP Issued 10/28/2009
    Consultant Contract Process Workhours Approved 10/26/2009