Project Description:
FRAMINGHAM- BIKE PATH CONSTRUCTION & IMPROVEMENTS ON COCHITUATE RAIL TRAIL, FROM SCHOOL STREET TO ROUTE 30
The project involves construction of rail trail amenities along the Cochituate Rail Trail, between School Street and Route 30, a distance of 1.4 miles. The work includes sidewalk construction, curbing, fences, bollards, benches, guard rail, pavement markings, landscaping and at-grade crossing equipment, if warranted.
Location:
  • Town of Framingham
  • Resident Engineer: Alan Webb
    Construction Contract Value: $1,058,517.00
    Construction Bid Price: $950,470.00
    Initial Construction Estimate: $829,170.50
    District: District 3

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 79735 -- Construction Contract
    Reconstruction and Related Work on a Section of the Cochituate Rail Trail. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/28/2010
    Project Initiation Form PIF Entered 04/28/2010
    Project Initiation Form PRC Submitted 05/17/2010
    Project Review Committee PRC Approved 05/13/2010
    Project Review Committee Letter 06/03/2010
    Project Status Advertised 09/14/2013
    Project Management
    100% Design 100% Package Received 08/05/2013
    100% Design 100% Package Comments to DE 09/06/2013
    25% Design 25% Package Received 10/17/2011
    25% Design 25% Package Comments to DE 11/10/2011
    25% Design Design Public Hearing 11/08/2012
    75% Design 75% Package Received 05/29/2013
    Final Design PS&E Received 09/11/2013
    Final Design PS&E to FAPRO 09/11/2013