FAIRHAVEN- BRIDGE SUPERSTRUCTURE REPLACEMENT, F-01-014, I-195 OVER RIVER AVENUE
The work on this project will consist of the replacing the entire superstructure of the bridge carrying I-195 over River Avenue in the Town of Fairhaven. Work will also include replacement of the existing superstructure with Prefabricated Bridge Units (Inverset), a new wearing surface, CF-PL3 guardrail, substructure crack repair, and limited approach roadway work.
Location:
  • Town of Fairhaven
  • Resident Engineer: Alfredo Nunez
    Construction Contract Value: $4,987,721.00
    Construction Bid Price: $4,186,549.50
    Initial Construction Estimate: $3,192,000.00
    District: District 5

    Contracts (3) Progress
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 73899 -- Construction Contract
    Bridge Superstructure Replacement using Accelerated Bridge Construction Techniques Br. No. F-01-014 Interstate 195 over River Avenue. (ABP) (RE-ADVERTISED) 100% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 09/13/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/03/2010
    Project Initiation Form PIF Entered 07/20/2010
    Project Initiation Form PRC Submitted 07/20/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Status Advertised 06/09/2012
    Project Management
    25% Design 25% Package Received 01/30/2012
    25% Design 25% Package Comments to DE 09/26/2011
    25% Design 25% Package Approved 03/12/2012
    25% Design Design Public Hearing 03/22/2012
    25% Design 25% Plans Complete 03/12/2012
    75% Design 75% Package Received 04/18/2012
    75% Design 75% Package Comments to DE 05/21/2012
    75% Design 75% Plans Approved 05/25/2012
    75% Design 75% Plans Complete 05/25/2012
    Final Design PS&E Received 05/25/2012
    Final Design PS&E to FAPRO 06/05/2012