Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BRIDGEWATER- RAYNHAM- TAUNTON- NORTON- INTERSTATE MAINTENANCE & RELATED WORK ON I-495
This project will consist of milling and resurfacing of I-495 beginning in Raynham at approximately Milemarker 18.3, then continuing northerly through the Towns of Bridgewater and Raynham and the City of Taunton, ending in the Town of Norton at Milemarker 25.2. Also included in the project are minor bridge repair and drainage structure repairs.
Location:
  • Town of Bridgewater
  • Town of Norton
  • Town of Raynham
  • City of Taunton
  • Resident Engineer: April Letourneau
    Construction Contract Value: $14,237,482.00
    Construction Bid Price: $12,341,675.45
    Initial Construction Estimate: $13,210,751.00
    District: District 5

    Contracts (1) Progress
    # 70919 -- Construction Contract
    Resurfacing and Related Work on a Section of Interstate 495 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/02/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/05/2010
    Project Initiation Form PIF Entered 07/29/2010
    Project Initiation Form PRC Submitted 07/29/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 09/02/2010
    Project Status Advertised 09/03/2011
    Project Management
    100% Design 100% Package Received 07/29/2011
    75% Design 75% Package Received 02/11/2011
    75% Design 75% Package Comments to DE 04/11/2011
    Final Design PS&E Received 08/03/2011
    Final Design PS&E to FAPRO 08/30/2011