Project Description:
MILFORD- SIGNAL & INTERSECTION IMPROVEMENTS ON ROUTE 16 (MAIN STREET & EAST MAIN STREET) AT 6 LOCATIONS
The project shall consist of traffic signal and minor geometric improvements to seven intersections along the Route 16 corridor in Milford, MA. The locations are Route 16 and: Cedar Street/Middleton Street, East Main Street/Beach Street, Winter Street/North Bow Street, School Street/Jefferson Street, Exchange Street/Central Street, South Main Street/Water Street. Signal coordination will be provided where applicable.
Location:
  • Town of Milford
  • Resident Engineer: Alan Webb
    Construction Contract Value: $3,501,790.00
    Construction Bid Price: $2,886,536.95
    Initial Construction Estimate: $3,041,781.50
    District: District 3

    Contracts (2) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 69636 -- Construction Contract
    MILFORD - Intersection Improvements and Related Work (Including Traffic Signals) on Route 16 (Main Street) and East Main Street at 6 Locations Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/21/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/07/2010
    Project Initiation Form PIF Entered 05/07/2010
    Project Initiation Form PRC Submitted 05/07/2010
    Project Review Committee PRC Approved 05/13/2010
    Project Review Committee Letter 06/03/2010
    Project Status Advertised 07/02/2011
    Project Management
    100% Design 100% Package Received 03/23/2011
    100% Design 100% Package Comments to DE 05/24/2011
    25% Design 25% Package Received 11/09/2010
    Final Design PS&E Received 06/14/2011
    Final Design PS&E to FAPRO 06/28/2011
    Consultant Contract Process Scope to DE 02/23/2010
    Consultant Contract Process NTP Issued 06/23/2010