Project Description:
NORTHBOROUGH- SHREWSBURY- RESURFACING & RELATED WORK ON ROUTE 20
The project involves resurfacing Route 20 from 0.25 miles west of South Street in Shrewsbury to Tomlin Hill Road in Northborough, for a total distance of 2.75 miles. Related work includes guardrail upgrades, drainage adjustments, pavement markings and traffic control.
Location:
  • Town of Northborough
  • Town of Shrewsbury
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Lyris Liautaud
    Estimated Total Contract Cost: $2,435,528.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project