Project Description:
DISTRICT 4- CORRECTIVE ACTIONS/WORK FOR NON-CONFORMING ISSUES ON ROUTE 3 (NORTH) BURLINGTON TO TYNGSBOROUGH
Work under this contract shall included the furnishing of all labor, equipment, and materials needed for various types of repairs to Route 3 including but not limited to the following categories: Earthwork and Excavation; Drainage Repairs; Pavement, Berm, and Shoulder Repairs; Highway Guardrail and Fence; Traffic Control Devices; Bridge and Concrete Repairs; and other Incidental Work as required throughout the duration of this contract. The work involved within each category may be completed in conjunction with other categories.
Location:
  • Town of Bedford
  • Town of Billerica
  • Town of Burlington
  • Town of Chelmsford
  • City of Lowell
  • Town of Tyngsborough
  • Resident Engineer: Cody Holemo
    Construction Contract Value: $2,810,000.00
    Construction Bid Price: $2,382,017.50
    Initial Construction Estimate: $2,066,211.00
    District: District 4

    Contracts (1) Progress
    # 71980 -- Construction Contract
    Roadway Repairs, Improvements and Related Work along a Section of Route 3 (North). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/13/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/13/2010
    Project Initiation Form PIF Entered 05/13/2010
    Project Initiation Form PRC Submitted 05/13/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 08/13/2010
    Project Status Advertised 11/26/2011
    Project Management
    Final Design PS&E Received 09/26/2011
    Final Design PS&E to FAPRO 11/21/2001