Project Description:
DISTRICT 1- DISTRICT 2- DISTRICT 3- DISTRICT 6- TOLL PLAZA SIGNING & PAVEMENT MARKING REPLACEMENT ON THE MASS PIKE (I-90) & MHS (US 1, SR 1A)
This project is to replace and improve the existing toll plaza signing and pavement markings on the Massachusetts Turnpike and certain roadways within the Metropolitan Highway System, in conformance with current MUTCD requirements for toll road signing and markings. These improved signs and markings will provide drivers with information about the locations of both electronic toll collection (EZPass) lanes and cash payment lanes as they approach the toll plazas.
Location:
  • Town of Auburn
  • City of Boston
  • City of Chelsea
  • City of Chicopee
  • Town of Framingham
  • Town of Lee
  • Town of Ludlow
  • Town of Millbury
  • Town of Natick
  • City of Newton
  • Town of Sturbridge
  • Town of West Springfield
  • Town of West Stockbridge
  • Town of Westborough
  • City of Westfield
  • Town of Weston
  • Resident Engineer: Anthony Tavalone
    Construction Contract Value: $1,389,821.30
    Construction Bid Price: $1,199,821.20
    Initial Construction Estimate: $1,518,332.20

    Contracts (1) Progress
    # 68907 -- Construction Contract
    Toll Plaza Signing and Pavement Marking Replacement on Sections of the Massachusetts Turnpike (I-90) and Route 1 and 1A. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/09/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/03/2010
    Project Initiation Form PIF Entered 06/11/2010
    Project Initiation Form PRC Submitted 06/11/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 12/22/2010
    Project Status Advertised 05/07/2011
    Project Management
    100% Design 100% Package Received 03/23/2011
    75% Design 75% Package Received 08/18/2010
    Final Design PS&E Received 04/22/2011
    Final Design PS&E to FAPRO 04/26/2011