NORTH ANDOVER- INTERSECTION & SIGNAL IMPROVEMENTS AT ROUTE 125 & MASSACHUSETTS AVENUE
The purpose of this project is to provide safety improvements at the intersection of Route 125 and Massachusetts Avenue. This work includes minor widening for turn lanes, geometric alignment, sidewalk construction, pavement markings, signage, signal upgrade and reconstructing wheelchair ramps.
Location:
  • Town of North Andover
  • Construction Begins: Summer 2019
    Resident Engineer: James Vayanos
    Construction Bid Price: $4,073,281.80
    District: District 4

    Contracts (3) Progress
    # 106817 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Chickering Road (Route 125/133) and Massachusetts Avenue Completed
    # 67008 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to the Highway Division on an open end basis for various high crash locations located in the Merrimack Valley. Final
    # 77853 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/14/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/10/2010
    Project Initiation Form PIF Entered 06/14/2010
    Project Initiation Form PRC Submitted 07/29/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 10/14/2010
    Project Status Advertised 01/12/2019
    Project Management
    100% Design 100% Package Received 04/27/2018
    100% Design 100% Package Comments to DE 07/11/2018
    25% Design 25% Package Received 10/02/2015
    25% Design 25% Package Comments to DE 01/21/2016
    25% Design Design Public Hearing 10/25/2016
    75% Design 75% Package Received 06/12/2017
    75% Design 75% Package Comments to DE 09/25/2017
    Final Design PS&E Received 11/09/2018
    Final Design PS&E Received - Resub 1 12/21/2018
    Consultant Contract Process NTP Issued 02/21/2012