Project Description:
HAVERHILL- IMPROVEMENTS ON MAIN STREET (ROUTE 125)
This project will improve safety at three locations along Route 125 in downtown Haverhill; Route 125 at Winter Street (Route 97) and Summer Street, Route 125 at Bailey Boulevard and Ginty Boulevard (Route 97) and Route 125 at Merrimack Street (Route 113) and Water Street (Route 113). The safety improvements will including geometric improvements, realignment, pavement markings, traffic signal upgrades and timing, sidewalk reconstruction and upgraded signage.
Location:
  • City of Haverhill
  • Construction Begins: Spring 2017
    Resident Engineer: Michael Cannata
    Construction Bid Price: $2,816,674.69
    District: District 4

    Contracts (3) Progress
    # 57793 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to the MassHighway on an open end basis located in the Merrimack Valley region. Final
    # 77884 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 97843 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) along Sections of Route 125 (Main Street) and Adjacent Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/12/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    Informational Meeting
    A public informational meeting for the conceptual design of this project is scheduled for 3/23/11 at 7:00 PM in Room 301 at Haverhill City Hall
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/15/2010
    Project Initiation Form PIF Entered 06/15/2010
    Project Initiation Form PRC Submitted 08/02/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 10/14/2010
    Project Status Advertised 09/17/2016
    Project Management
    100% Design 100% Package Received 07/15/2016
    100% Design 100% Package Comments to DE 08/22/2016
    25% Design 25% Package Received 09/10/2012
    25% Design 25% Package Comments to DE 03/30/2015
    25% Design Design Public Hearing 11/18/2015
    75% Design 75% Package Received 02/04/2016
    75% Design 75% Package Comments to DE 04/04/2016
    Final Design PS&E Received 09/01/2016
    Final Design PS&E to Peer Reviewer 07/29/2016
    Final Design Peer Review Comments to DE 09/12/2016
    Final Design PS&E to FAPRO 09/12/2016
    Consultant Contract Process Scope to DE 12/14/2009
    Consultant Contract Process NTP Issued 03/16/2010
    Consultant Contract Process Workhours Approved 02/11/2010