Project Description:
LEXINGTON- BURLINGTON- INTERSTATE MAINTENANCE & RELATED WORK ON I-95
The project consists of highway and bridge deck resurfacing, median barrier, safety and environmental improvements. The project limits are from MM 44.9 to MM 51.8 for a total project length of 6.9 miles.
Location:
  • Town of Burlington
  • Town of Lexington
  • Construction Begins: Spring 2014
    Resident Engineer: Gennady Shkolnikov
    Construction Contract Value: $26,608,994.00
    Construction Bid Price: $20,440,049.40
    Initial Construction Estimate: $20,841,520.00
    District: District 4

    Contracts (3) Progress
    # 56818 -- Design -- Services
    Work will consist of providing statewide photogrammetric services on an as need, assignment basis over a period of 60 months. Final
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 79516 -- Construction Contract
    Resurfacing and Related Work Including Median Barrier and 2 Bridges along a Section of Interstate 95. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/25/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/21/2010
    Project Initiation Form PIF Entered 08/09/2011
    Project Initiation Form PRC Submitted 08/09/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 08/31/2013
    Project Management
    100% Design 100% Package Received 08/13/2013
    25% Design 25% Package Received 05/17/2013
    75% Design 75% Package Received 05/17/2013
    75% Design 75% Package Comments to DE 06/17/2013
    Final Design PS&E Received 08/19/2013
    Final Design PS&E to FAPRO 08/21/2013
    Final Design PS&E to FAPRO 01/08/2014