| Project Description: |
SHARON- INTERSTATE MAINTENANCE & RELATED WORK ON I-95
Interstate maintenance, pavement preservation, safety and related work from MM 16.5 to MM 20.7 for a total project length of 4.20 miles.
|
| Location: |
|
| Construction Begins: | Autumn 2014 |
| Resident Engineer: | Brian Lewis![]() |
| Construction Contract Value: | $8,342,341.00 |
| Construction Bid Price: | $7,248,399.50 |
| Initial Construction Estimate: | $6,648,504.50 |
| District: | District 5 |
|
Bridges
|
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||