Project Description:
BOURNE- RESURFACING & RELATED WORK ON ROUTE 28
Work on this project includes roadway resurfacing (mill and overlay) of the existing roadway. Drainage improvements, bridge work, safety improvements and associated work will also be included in this contract. The project extends along Route 28 from the South side of the Bourne Bridge to the Bourne/Falmouth Town Line (MM 56.5 to MM 63) for a total project length of 6.5 miles.
Location:
  • Town of Bourne
  • Resident Engineer: Malcolm Lavalley
    Construction Contract Value: $8,520,667.84
    Construction Bid Price: $7,389,353.40
    Initial Construction Estimate: $6,712,000.00
    District: District 5

    Contracts (3) Progress
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64301 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 83242 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 28 (MacArthur Boulevard). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/11/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/21/2010
    Project Initiation Form PIF Entered 10/21/2010
    Project Initiation Form PRC Submitted 10/21/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/23/2010
    Project Status Advertised 07/05/2014
    Project Management
    100% Design 100% Package Received 10/31/2013
    100% Design 100% Package Received 05/16/2014
    100% Design 100% Package Comments to DE 01/29/2014
    75% Design 75% Package Received 01/30/2013
    75% Design 75% Package Comments to DE 10/18/2013
    Final Design PS&E Received 03/10/2014
    Final Design PS&E Received 05/16/2014
    Final Design PS&E Received 06/02/2015
    Final Design PS&E to FAPRO 06/27/2014
    Final Design PS&E to FAPRO 03/10/2015