Project Description: |
BOSTON- SUBSTRUCTURE REPAIR TO B-16-458 (LEVERETT CIRCLE UNDERPASS)
Proposed project will address deteriorated concrete on the substructure of a bridge in District 6.
|
Location: |
|
Resident Engineer: | Eric Mistretta |
Construction Contract Value: | $2,374,155.00 |
Construction Bid Price: | $2,184,435.00 |
Initial Construction Estimate: | $1,811,512.50 |
District: | District 6 |
|
Bridges
|
|
|
|
|