Project Description:
LOWELL- IMPROVEMENTS ON ROUTE 38 AT FOUR INTERSECTIONS
The project will upgrade signals and intersection geometry to address crash potential at four intersections along the Route 38 corridor: Rogers Street (Route 38) at Phoenix Avenue and Douglas Road, Rogers Street (Route 38) at Boylston Street, Nesmith Street (Route 38) at Andover Street (Route 133/110), and Nesmith Street (Route 38) at East Merrimack Street. Some improvements at Nesmith Street and Stackpole Street will be included for interconnection.
Location:
  • City of Lowell
  • Construction Begins: Spring 2019
    Construction Ends: Summer 2021
    Resident Engineer: -- not assigned --
    Construction Bid Price: $3,844,640.13
    District: District 4
    Current Status: Contractor has mobilized and cleared trees that will impact road widening areas. (as of 09/10/2019)
    Additional Info: Utility work is scheduled to begin late September, pole relocations are to facilitate roadwork, new traffic signals and road widenings. (as of 09/10/2019)

    Contracts (4) Status
    # 101631 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide and bridge projects, for the purpose of maintaining Final
    # 105927 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at 4 Locations Route 38 (Rogers/Nesmith Streets).
    # 63995 -- Design -- Hwy Eng Open End
    Work will consist of facilitating Road Safety Audits and providing engineering design services on an open end basis for high crash locations in Northern Middlesex region. Final
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/25/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractor has mobilized and cleared trees that will impact road widening areas.
    Additional Info
    Utility work is scheduled to begin late September, pole relocations are to facilitate roadwork, new traffic signals and road widenings.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/29/2010
    Project Initiation Form PIF Entered 11/29/2010
    Project Initiation Form PRC Submitted 11/03/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 09/15/2018
    Project Management
    100% Design 100% Package Received 03/02/2018
    100% Design 100% Package Received 03/02/2018
    25% Design 25% Package Received 02/26/2016
    25% Design 25% Package Comments to DE 06/07/2016
    25% Design Design Public Hearing 07/28/2016
    75% Design 75% Package Received 06/30/2017
    75% Design 75% Package Comments to DE 09/27/2017
    Final Design PS&E Received 03/02/2018