SPENCER- REHABILITATION ON ROUTE 9 (MAIN STREET), FROM HIGH STREET TO GROVE STREET
Roadway reconstruction, geometric improvements, sidewalk and accessibility improvements, improvements to water, sewer and drainage systems.
Location:
  • Town of Spencer
  • Construction Begins: Autumn 2016
    Resident Engineer: Hassan Valipour
    Construction Bid Price: $3,122,905.00
    District: District 3

    Contracts (1) Progress
    # 96792 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 9 (Main Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/07/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/09/2010
    Project Initiation Form PIF Entered 08/02/2010
    Project Initiation Form PRC Submitted 08/09/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Status Advertised 08/06/2016
    Project Management
    100% Design 100% Package Received 05/24/2016
    100% Design 100% Package Comments to DE 06/28/2016
    25% Design 25% Package Received 12/08/2013
    25% Design 25% Package Comments to DE 03/17/2014
    25% Design Design Public Hearing 12/09/2014
    75% Design 75% Package Received 09/08/2015
    75% Design 75% Package Comments to DE 11/09/2015
    Final Design PS&E Received 07/22/2016
    Final Design PS&E to Peer Reviewer 07/25/2016
    Final Design Peer Review Comments to DE 08/08/2016
    Final Design PS&E to FAPRO 08/01/2016
    Final Design PS&E Received - Resub 1 08/30/2016