Project Description:
FRAMINGHAM- RECONSTRUCTION OF ROUTE 126 (CONCORD STREET)
The work under this project will rehabiltate Route 126, add turn lanes, improve sidewalks and curbing, upgrade the existing traffic signal system and replace the roundabout at Concord Street @ Union Avenue with a new traffic signal.
Location:
  • Town of Framingham
  • Resident Engineer: Alan Webb
    Construction Contract Value: $8,280,396.50
    Construction Bid Price: $8,791,402.00
    Initial Construction Estimate: $700,073.00
    District: District 3

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 79745 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Concord Street (Route 126) and Adjacent Streets (Including Traffic Signals and Street Lighting). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/14/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/09/2010
    Project Initiation Form PIF Entered 08/02/2010
    Project Initiation Form PRC Submitted 08/09/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Status Advertised 09/14/2013
    Project Management
    100% Design 100% Package Received 07/09/2013
    100% Design 100% Package Comments to DE 08/28/2013
    25% Design 25% Package Received 09/24/2010
    25% Design 25% Package Comments to DE 06/30/2011
    25% Design 25% Package Approved 07/13/2012
    25% Design Design Public Hearing 09/27/2012
    75% Design 75% Package Received 02/22/2013
    75% Design 75% Package Comments to DE 05/01/2013
    Final Design PS&E Received 09/09/2013
    Final Design PS&E to FAPRO 09/09/2013
    Final Design PS&E to FAPRO 12/31/2013