Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SCITUATE- SAFE ROUTES TO SCHOOL (HATHERLY ELEMENTARY SCHOOL)
Work on this project consists of the installation of a walk for 2600 feet on Hollett Street. New crosswalks and wheelchair ramps will be installed at 3 intersections.
Location:
  • Town of Scituate
  • Resident Engineer: Peter Benkart
    Construction Contract Value: $400,035.00
    Construction Bid Price: $348,277.50
    Initial Construction Estimate: $390,895.00
    District: District 5

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70212 -- Construction Contract
    Sidewalk Reconstruction and Related Work on a Section of Hollett Street (Safe Routes to Hatherly School). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/20/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/22/2010
    Project Initiation Form PIF Entered 07/23/2010
    Project Initiation Form PRC Submitted 07/26/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 08/30/2010
    Project Status Advertised 07/30/2011
    Project Management
    100% Design 100% Package Received 03/21/2011
    100% Design 100% Package Comments to DE 06/03/2011
    100% Design 100% Plans Approved 06/10/2011
    25% Design 25% Package Received 10/19/2010
    25% Design 25% Package Comments to DE 12/23/2010
    25% Design 25% Package Approved 03/09/2011
    25% Design Design Public Hearing 03/08/2011
    75% Design 75% Package Received 05/03/2011
    Final Design PS&E Received 06/21/2011
    Consultant Contract Process Scope to DE 01/12/2010
    Consultant Contract Process NTP Issued 02/08/2010