Project Description:
HARDWICK- RESURFACING & RELATED WORK ON THE GILBERTVILLE SECTIONS OF ROUTES 32 AND 32A
Work under this project will consist of milling and overlaying the existing pavement with some sections of full-depth repair. Work will also include geometric improvements and driveway consolidation at the Route 32A intersection. New concrete sidewalks, granite curbing and drainage is proposed throughout. Also included will be new signage and pavement markings. The project extends from the end of state highway just north of High Street northerly to Upper Church Street on Route 32, and from Route 32 to Mechanic Street on Route 32A.
Location:
  • Town of Hardwick
  • Construction Begins: Autumn 2021
    Resident Engineer: Guilherme Fill
    Construction Bid Price: $4,739,393.00
    District: District 2

    Contracts (1) Progress
    # 115353 -- Construction Contract
    Resurfacing and Related Work (Including Br. No. H-08-22) on Sections of Main/Church Street (Route 32), Hardwick Road (Route 32A) and Adjacent Streets Completed

    Bridges

    Contract Dates
    Notice to Proceed: 09/27/2021
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/26/2010
    Project Initiation Form PIF Entered 07/29/2010
    Project Initiation Form PRC Submitted 07/30/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 10/14/2010
    Project Status Advertised 07/17/2021
    Project Management
    100% Design 100% Package Received 10/28/2019
    25% Design 25% Package Received 04/28/2017
    25% Design Design Public Hearing 04/24/2018
    75% Design 75% Package Received 12/10/2018
    75% Design 75% Package Comments to DE 05/10/2019
    Final Design PS&E Received 10/09/2020
    Final Design PS&E Received - Resub 1 03/03/2021
    Final Design PS&E Received - Resub 2 04/09/2021