Project Description:
ACTON- CONCORD- BRUCE FREEMAN RAIL TRAIL CONSTRUCTION, INCLUDES REPLACING BRIDGE C-19-037, RAIL TRAIL OVER NASHOBA BROOK, NEW BRIDGE C-19-039, RAIL TRAIL OVER ROUTE 2 & NEW CULVERT C-19-040, ROUTE 2 OVER WILDLIFE CROSSING (PHASE II-B)
This rail to trail project begins at the intersection of Weatherbee Street and Great Road in Acton and continues across Route 2 to Commonwealth Avenue in Concord. This portion of the trail will connect the Bruce Freeman trail across Route 2 between Concord and Acton. The total approximate project length is 5500 feet, 1.04 Miles.
Location:
  • Town of Acton
  • Town of Concord
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Michael Winnick
    Construction Bid Price: $9,957,790.50
    District: District 4

    Contracts (2) Progress
    # 109678 -- Construction Contract
    Construction of the Bruce Freeman Rail Trail (BFRT) (Phase 2B) Completed
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 02/28/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/28/2010
    Project Initiation Form PIF Entered 07/28/2010
    Project Initiation Form PRC Submitted 07/29/2010
    Project Review Committee PRC Approved 02/25/1997
    Project Status Advertised 09/14/2019
    Project Management
    100% Design 100% Package Received 02/08/2019
    100% Design 100% Package Comments to DE 04/17/2019
    25% Design 25% Package Received 02/26/2016
    25% Design 25% Package Comments to DE 07/06/2016
    25% Design 25% Package Received - Resub 1 09/22/2016
    25% Design Design Public Hearing 11/17/2016
    75% Design 75% Package Received 06/28/2018
    75% Design 75% Package Comments to DE 09/04/2018
    Final Design PS&E Received 06/18/2019
    Final Design PS&E to FAPRO 08/26/2019