Project Description:
EASTON- SAFE ROUTES TO SCHOOL (F.L. OLMSTED SCHOOL)
Work on this project includes the construction of an 8 foot wide sidewalk from the intersection of Western Avenue and Columbus Avenue to Lothrop Street. A retaining wall is required to construct the walk and a crosswalk will also be constructed.
Location:
  • Town of Easton
  • Resident Engineer: John Bielski
    Construction Contract Value: $521,462.71
    Construction Bid Price: $396,950.50
    Initial Construction Estimate: $438,490.00
    District: District 5

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 73147 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Western Avenue (Safe Routes to Olmsted, Richardson, Parkview, and Easton Middle Schools). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/11/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/30/2010
    Project Initiation Form PIF Entered 07/30/2010
    Project Initiation Form PRC Submitted 07/30/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 08/30/2010
    Project Status Advertised 03/24/2012
    Project Management
    100% Design 100% Package Received 01/12/2012
    100% Design 100% Package Comments to DE 02/21/2012
    25% Design 25% Package Received 09/01/2011
    25% Design 25% Package Comments to DE 11/08/2011
    25% Design Design Public Hearing 12/15/2011
    Final Design PS&E Received 03/05/2012
    Consultant Contract Process NTP Issued 01/28/2011