LOWELL- SAFE ROUTES TO SCHOOLS (MCAULIFFE ELEMENTARY SCHOOL & ROBINSON MIDDLE SCHOOL)
This project includes resurfacing for June Street from the School Driveway to 13th Street, constructing sidewalk on the east side of Beacon Street and installing a flashing pedestrian warning assembly north of the School Driveway, adding a sidewalk along the outside of the semi-circular School Driveway and reconstructing the sidewalk on the west side of June Street.
Location:
  • City of Lowell
  • Resident Engineer: Desire Manirakiza
    Construction Contract Value: $505,730.08
    Construction Bid Price: $418,914.55
    Initial Construction Estimate: $462,815.00
    District: District 4

    Contracts (2) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 70650 -- Construction Contract
    Sidewalk Reconstruction and Related Work on a Section of Beacon, June, 13th Streets and School Entrance Driveway (Safe Routes to McAuliffe Elementary and Robinson Middle Schoo Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/12/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/02/2010
    Project Initiation Form PIF Entered 08/02/2010
    Project Initiation Form PRC Submitted 08/02/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 08/30/2010
    Project Status Advertised 08/20/2011
    Project Management
    100% Design 100% Package Received 05/17/2011
    100% Design 100% Package Comments to DE 06/17/2011
    25% Design 25% Package Received 10/28/2010
    25% Design 25% Package Comments to DE 12/14/2010
    25% Design Design Public Hearing 03/07/2011
    75% Design 75% Package Received 10/28/2010
    Final Design PS&E Received 08/09/2011
    Final Design PS&E to FAPRO 08/09/2011
    Consultant Contract Process Scope to DE 01/11/2010
    Consultant Contract Process NTP Issued 04/13/2010