Project Description:
DISTRICT 5- ROUTINE BRIDGE MAINTENANCE ON ROUTE 24 CORRIDOR
Work under this contract will consist of performing routine bridge maintenance activities on bridges on/over Route 24 in District 5.
Location:
Resident Engineer: Alex Lustikman
Construction Contract Value: $5,105,810.71
Construction Bid Price: $4,724,006.00
Initial Construction Estimate: $4,676,114.00
District: District 5

Contracts (1) Progress
# 70726 -- Construction Contract
Cleaning, Painting and Structural Repairs to 25 Bridges on the Route 24 Corridor (Fall River to Stoughton). Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/23/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/03/2010
    Project Initiation Form PIF Entered 08/03/2010
    Project Initiation Form PRC Submitted 08/03/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 11/30/2010
    Project Status Advertised 08/27/2011
    Project Management
    Final Design PS&E Received 08/04/2011
    Final Design PS&E to FAPRO 08/19/2011
    Final Design PS&E to FAPRO 08/25/2011