Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
AMHERST- SAFE ROUTES TO SCHOOL (WILDWOOD ELEMENTARY & AMHERST REGIONAL MIDDLE SCHOOL)
The proposed pedestrian safety/access improvement project will include a pedestrian flashing assembly and upgraded crossing at East Pleasant Street and Strong Street, approximately 1100’ of sidewalk with a grass panel on the west side of the Amherst Middle School Driveway and a raised crossing and new bike shelter at the Wildwood Elementary School entrance. The proposed improvements will also include upgraded wheelchair ramps, new pavement markings, new traffic and pedestrian warning signs, and some minor drainage modifications.
Location:
  • Town of Amherst
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $323,527.00
    Construction Bid Price: $280,485.05
    Initial Construction Estimate: $335,645.00
    District: District 2

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70917 -- Construction Contract
    Sidewalk Reconstruction and Related Work on Sections of East Pleasant, Strong and Chestnut Streets (Safe Routes to the Wildwood Elementary and the Amherst Regional Middle Scho Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/05/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/03/2010
    Project Initiation Form PIF Entered 08/03/2010
    Project Initiation Form PRC Submitted 08/04/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 08/30/2010
    Project Status Advertised 09/03/2011
    Project Management
    100% Design 100% Package Received 04/01/2011
    100% Design 100% Package Comments to DE 05/20/2011
    25% Design 25% Package Received 12/28/2010
    25% Design 25% Package Comments to DE 02/22/2011
    25% Design Design Public Hearing 03/24/2011
    75% Design 75% Package Received 12/28/2010
    75% Design 75% Package Comments to DE 02/22/2011
    Final Design PS&E Received 06/07/2011
    Final Design PS&E to FAPRO 08/31/2011