Project Description:
PITTSFIELD- INTERSECTION & SIGNAL IMPROVEMENTS AT FIRST STREET & NORTH STREET (NEAR BERKSHIRE MEDICAL CENTER)
This project is recommended in the Berkshire regionís current RTP, and was conceptualized and analyzed in the MPO approved Pittsfield Downtown Circulation Study (Fuss & OíNeill - 2006). The project includes intersection widening and signalization improvements at First and Tyler St; the closure of North St between Tyler and Stoddard Ave; the realignment of Charles St with Springside Ave at North St; and intersection modifications (includes installing traffic signal) at Stoddard Ave/North St at Berkshire Medical Centerís main entrance.
Location:
  • City of Pittsfield
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2022/2023
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $4,258,416.98
    Estimated Total Federal Participating Construction Cost: $4,979,287.16
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: Design Public Hearing (as of 06/30/2021 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: PITTSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • STBG + CMAQ + HSIP; Total Project Cost = 7,040,196; YOE = 8%
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $434,275.20
    State Cost: $48,252.80
    Total Cost: $482,528.00

    Planned Federal FY: 2023
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: PITTSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • STBG + CMAQ + HSIP; Total Project Cost = 7,040,196; YOE = 8%
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $544,968.00
    State Cost: $136,242.00
    Total Cost: $681,210.00

    Planned Federal FY: 2023
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: PITTSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • STBG + CMAQ + HSIP; Total Project Cost = 7,040,196; YOE = 8%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,701,166.40
    State Cost: $1,175,291.60
    Total Cost: $5,876,458.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/04/2010
    Project Initiation Form PIF Entered 08/06/2010
    Project Initiation Form PRC Submitted 08/06/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 04/29/2011
    Project Management
    25% Design 25% Package Received 07/27/2020
    25% Design 25% Package Comments to DE 10/27/2020
    25% Design Design Public Hearing 06/30/2021