PITTSFIELD- INTERSECTION & SIGNAL IMPROVEMENTS AT FIRST STREET & NORTH STREET (NEAR BERKSHIRE MEDICAL CENTER)
This project is recommended in the Berkshire region’s current RTP, and was conceptualized and analyzed in the MPO approved Pittsfield Downtown Circulation Study (Fuss & O’Neill - 2006). The project includes intersection widening and signalization improvements at First and Tyler St; the closure of North St between Tyler and Stoddard Ave; the realignment of Charles St with Springside Ave at North St; and intersection modifications (includes installing traffic signal) at Stoddard Ave/North St at Berkshire Medical Center’s main entrance.
Location:
  • City of Pittsfield
  • Construction Begins: Autumn 2023
    Resident Engineer: Cathy Spaniol
    Construction Bid Price: $7,469,061.99
    District: District 1

    Contracts (1) Progress
    # 124019 -- Construction Contract
    Intersection & Signal Improvements at First Street & North Street (Near Berkshire Medical Center) 4% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/01/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/04/2010
    Project Initiation Form PIF Entered 08/06/2010
    Project Initiation Form PRC Submitted 08/06/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 04/29/2011
    Project Status Advertised 09/09/2023
    Project Management
    100% Design 100% Package Received 03/02/2023
    100% Design 100% Package Comments to DE 04/07/2023
    25% Design 25% Package Received 07/27/2020
    25% Design 25% Package Comments to DE 10/27/2020
    25% Design Design Public Hearing 06/30/2021
    75% Design 75% Package Received 11/23/2022
    75% Design 75% Package Comments to DE 12/30/2022
    Final Design PS&E Received 06/26/2023
    Final Design PS&E Received - Resub 1 08/11/2023