Project Description:
QUINCY- ADAMS GREEN TRANSPORTATION IMPROVEMENTS
The project involves the creation of a new public space. The design features: (1) Discontinuing the southerly portion of Hancock Street, (2) Converting Washington Street between Hancock Street and Temple Streets from one-way to a two-way roadways. and (3) Converting Temple Street between Washington Street and Hancock Street from a one-way to a two-way roadway.
Location:
  • City of Quincy
  • Resident Engineer: Scott Leisey
    Construction Contract Value: $8,269,885.00
    Construction Bid Price: $7,911,175.00
    Initial Construction Estimate: $6,638,872.00
    District: District 6

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 78210 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals) on Sections of Hancock and Adjacent Streets Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/06/2013
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/06/2010
    Project Initiation Form PIF Entered 08/06/2010
    Project Initiation Form PRC Submitted 08/06/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 12/02/2010
    Project Status Advertised 06/29/2013
    Project Management
    100% Design 100% Package Received 12/20/2012
    100% Design 100% Package Comments to DE 03/18/2013
    25% Design 25% Package Received 04/12/2012
    25% Design 25% Package Comments to DE 06/20/2012
    25% Design Design Public Hearing 06/13/2012
    75% Design 75% Package Received 09/04/2012
    75% Design 75% Package Comments to DE 11/02/2012
    Final Design PS&E Received 06/05/2013
    Final Design PS&E to FAPRO 06/10/2013