Project Description:
CHELSEA- SAFE ROUTES TO SCHOOL AT WRIGHT & BROWNE SCHOOLS @ WALNUT, 5TH, 6TH, & ARLINGTON STREETS
This project involves undertaking sidewalk modifications and creating curb bump outs to increase pedestrian traffic safety adjacent to two schools.
Location:
  • City of Chelsea
  • Resident Engineer: Robert O'Neil
    Construction Contract Value: $434,000.25
    Construction Bid Price: $377,554.65
    Initial Construction Estimate: $391,795.00
    District: District 6

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70378 -- Construction Contract
    Sidewalk Reconstruction and Related Work on Sections of Arlington, 5th, 6th and Walnut Streets (Safe Routes to Browne and Wright Schools). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/18/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/20/2010
    Project Initiation Form PIF Entered 08/20/2010
    Project Initiation Form PRC Submitted 08/20/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 08/30/2010
    Project Status Advertised 08/06/2011
    Project Management
    100% Design 100% Package Received 05/27/2011
    100% Design 100% Package Comments to DE 07/22/2011
    25% Design 25% Package Received 01/03/2011
    25% Design Design Public Hearing 04/26/2011
    75% Design 75% Package Received 01/03/2011
    75% Design 75% Package Comments to DE 05/02/2011
    Final Design PS&E Received 07/25/2011
    Final Design PS&E to FAPRO 08/02/2011
    Consultant Contract Process Scope to DE 09/10/2010
    Consultant Contract Process NTP Issued 09/27/2010