Project Description:
DISTRICT 3- TREE TRIMMING & SITE DISTANCE CLEARING FOR UTILITY RELOCATIONS
This project is a pilot project under the ABP program to attempt to minimize the delays cause by utility relocations during construction. This contract will be used to clear relocation areas for utility companies, prior to the commencement of our construction projects.
Location:
Resident Engineer: Mohamed Zawahreh
Construction Contract Value: $157,050.00
Construction Bid Price: $136,050.00
Initial Construction Estimate: $196,250.00
District: District 3

Contracts (1) Progress
# 67815 -- Construction Contract
Tree Trimming and Removal at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/24/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/26/2010
    Project Initiation Form PIF Entered 08/26/2010
    Project Initiation Form PRC Submitted 09/07/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/22/2010
    Project Status Advertised 12/18/2010
    Project Management
    100% Design 100% Plans Complete 11/08/2010
    Final Design PS&E Received 11/23/2010