Project Description:
PLYMOUTH- IMPROVEMENTS ON OBERY STREET, FROM SOUTH STREET TO A.A. CARANCI WAY/PLYMOUTH NORTH H.S. DRIVE INTERSECTION
Work on this project includes geometric improvements along Obery Street including a roundabout at the court house entrance and high school entrance, a new traffic signal system at the South Street/Obery Street intersection, and new sidewalks. The roadway will be widened to improve bicycle accommodation. The project also includes drainage upgrades, new pavement marking and signs.
Location:
  • Town of Plymouth
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2018
    Project Manager: Filbert Yee
    Estimated Total Federal Participating Construction Cost: $6,753,596.25
    Estimated Total Contract Cost: $6,244,984.80
    Funding Provision: This project is planned to be funded through the 2018 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 08/18/2018 )

    Contracts (0) Status
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2018
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: PLYMOUTH
    Category: Advertised Projects Constr.
    Budget Section: UNK

  • a) Construction; b) Total Project Cost = $6,657,553 w/ $5,660,125 of STP funding and $997,428 of Statewide STP funding; d) MPO score 7.97
  • Category Surface Transportation Program
    Federal Cost: $4,528,100.00
    State Cost: $1,132,025.00
    Total Cost: $5,660,125.00

    Planned Federal FY: 2018
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: PLYMOUTH
    Category: Advertised Projects Constr.
    Budget Section: 1C

  • a) Construction; b) Total Project Cost = $6,657,553 w/ $5,660,125 of STP funding and $997,428 of Statewide STP funding; d) MPO score 7.97
  • Category Surface Transportation Program
    Federal Cost: $797,942.40
    State Cost: $199,485.60
    Total Cost: $997,428.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/30/2010
    Project Initiation Form PIF Entered 08/30/2010
    Project Initiation Form PRC Submitted 09/14/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/24/2010
    Project Status Advertised 08/18/2018
    Project Management
    100% Design 100% Package Received 04/24/2017
    100% Design 100% Package Comments to DE 07/27/2017
    25% Design 25% Package Received 09/30/2011
    25% Design 25% Package Received 02/28/2014
    25% Design 25% Package Comments to DE 03/13/2013
    25% Design Design Public Hearing 01/19/2017
    75% Design 75% Package Received 09/30/2011
    75% Design 75% Package Received 02/28/2014
    75% Design 75% Package Comments to DE 03/13/2013
    Final Design PS&E Received 06/18/2018
    Final Design PS&E to Peer Reviewer 06/28/2018
    Final Design Peer Review Comments to DE 07/13/2018
    Final Design PS&E to FAPRO 08/06/2018