Project Description:
PLYMOUTH- IMPROVEMENTS ON OBERY STREET, FROM SOUTH STREET TO A.A. CARANCI WAY/PLYMOUTH NORTH H.S. DRIVE INTERSECTION
Work on this project includes geometric improvements along Obery Street including a roundabout at the court house entrance and high school entrance, a new traffic signal system at the South Street/Obery Street intersection, and new sidewalks. The roadway will be widened to improve bicycle accommodation. The project also includes drainage upgrades, new pavement marking and signs.
Location:
  • Town of Plymouth
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Dylan Hipolito
    Construction Bid Price: $5,320,845.00
    District: District 5

    Contracts (1) Progress
    # 105571 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals and 2 Roundabouts) along Sections of South and Obery Streets Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/11/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/30/2010
    Project Initiation Form PIF Entered 08/30/2010
    Project Initiation Form PRC Submitted 09/14/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/24/2010
    Project Status Advertised 08/18/2018
    Project Management
    100% Design 100% Package Received 04/24/2017
    100% Design 100% Package Comments to DE 07/27/2017
    100% Design 100% Package Received - Resub 1 12/27/2017
    25% Design 25% Package Received 09/30/2011
    25% Design 25% Package Received 02/28/2014
    25% Design 25% Package Comments to DE 03/13/2013
    25% Design 25% Package Received - Resub 2 07/13/2016
    25% Design Design Public Hearing 01/19/2017
    75% Design 75% Package Received 09/30/2011
    75% Design 75% Package Received 02/28/2014
    75% Design 75% Package Comments to DE 03/13/2013
    75% Design 75% Package Received - Resub 2 07/13/2016
    Final Design PS&E Received 06/18/2018
    Final Design PS&E to Peer Reviewer 06/28/2018
    Final Design Peer Review Comments to DE 07/13/2018
    Final Design PS&E to FAPRO 08/06/2018
    Final Design PS&E Received - Resub 1 07/24/2018