Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BARNSTABLE- INTERSECTION IMPROVEMENTS AT IYANOUGH ROAD (ROUTE 28) AND YARMOUTH ROAD
Work on this project consists of intersection reconstruction and traffic signal upgrades. The intent of the project is to improve safety and reduce congestion for all users at the intersection of Iyanough Road (Route 28) and Yarmouth Road. Additional approach turn lanes are required at the intersection to alleviate congestion and improve corridor/intersection level of service. A new traffic signal system will be installed. New rails, gates and signals will be installed for the rail crossing. A shared use path will be constructed on the west side of Yarmouth Road crossing at Route 28, then connecting to Engine House Road at the entrance to the intermodal center. The remaining quadrants will have new sidewalks. Also included in the project are to new pavement markings and signage.
Location:
  • Town of Barnstable
  • Construction Begins: Autumn 2021
    Resident Engineer: Michael King
    Construction Bid Price: $17,867,914.00
    District: District 5
    Current Status: Contractor has secured construction operations until 11/18/24. Scheduled work hours are Monday through Friday 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 11/07/2024)

    Contracts (5) Progress
    # 114724 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Iyannough (Route 28) and Yarmouth Roads (Re-Advertised Project) 65% Complete
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/06/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractor has secured construction operations until 11/18/24. Scheduled work hours are Monday through Friday 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/07/2010
    Project Initiation Form PIF Entered 09/08/2010
    Project Initiation Form PRC Submitted 09/08/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/23/2010
    Project Status Advertised 09/14/2019
    Project Status Advertised 06/05/2021
    Project Management
    100% Design 100% Package Received 07/25/2018
    100% Design 100% Package Comments to DE 10/25/2018
    25% Design 25% Package Received 10/10/2014
    25% Design 25% Package Comments to DE 04/28/2015
    25% Design Design Public Hearing 02/18/2016
    75% Design 75% Package Received 03/03/2017
    75% Design 75% Package Comments to DE 06/29/2017
    75% Design 75% Package Received - Resub 1 08/30/2017
    75% Design 75% Plans Approved 09/12/2017
    Final Design PS&E Received 05/31/2019
    Final Design PS&E to FAPRO 08/26/2019
    Final Design PS&E Received - Resub 1 05/31/2019
    Final Design PS&E Received - Resub 2 08/28/2019
    Final Design PS&E Received - Resub 3 12/06/2019
    Final Design PS&E Received - Resub 4 02/18/2020
    Final Design PS&E Received - Resub 5 11/12/2020
    Final Design PS&E Received - Resub 5 01/28/2021