DISTRICT 4- SCHEDULED & EMERGENCY DECK AND JOINT REPAIRS AT VARIOUS LOCATIONS
These are emergency and scheduled maintenance projects and must be in place all the time. Existing Contract 62025 expires on March 1, 2011 and more than 85% encumbered funds are already spent. This new contract must be in place before we run out of money on the existing contract or before March 1, 2011, whichever is earlier.
Location:
Resident Engineer: Thomas Zizza
Construction Contract Value: $2,770,270.00
Construction Bid Price: $2,434,770.00
Initial Construction Estimate: $3,127,850.00
District: District 4

Contracts (1) Progress
# 68135 -- Construction Contract
Scheduled and Emergency Deck and Joint Repairs at Various Locations District Wide Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/20/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/10/2010
    Project Initiation Form PIF Entered 09/10/2010
    Project Initiation Form PRC Submitted 09/10/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/22/2010
    Project Status Advertised 01/01/2011
    Project Management
    Final Design PS&E Received 04/27/2011