HOPKINTON TO ANDOVER- INSTALLATION OF CAMERAS, MESSAGE SIGNS & COMMUNICATION INFRASTRUCTURE ON I-495 (DESIGN-BUILD)
Design-Build Intelligent Transportation Systems project on I-495 between I-90 and I-93. Install cameras, changeable message signs, vehicle detectors and communications infrastructure. There is existing fiber previously installed by C2C in the median which will be used for this project.
Location:
  • Town of Andover
  • Town of Berlin
  • Town of Bolton
  • Town of Boxborough
  • Town of Chelmsford
  • Town of Harvard
  • Town of Hopkinton
  • Town of Hudson
  • Town of Littleton
  • City of Lowell
  • City of Marlborough
  • Town of Southborough
  • Town of Tewksbury
  • Town of Westborough
  • Town of Westford
  • Resident Engineer: Arvind Patel
    Construction Contract Value: $9,736,900.00
    Construction Bid Price: $8,629,000.00
    Initial Construction Estimate: $6,289,000.00

    Contracts (1) Progress
    # 77307 -- Construction Contract
    Construction of the Advanced Transportation Management Systems (ATMS) along a Section of Interstate 495. 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/27/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/20/2010
    Project Initiation Form PIF Entered 09/20/2010
    Project Initiation Form PRC Submitted 09/20/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/24/2010
    Project Status Advertised 09/14/2013
    Project Management
    25% Design 25% Package Received 03/30/2011
    25% Design 25% Package Received 08/14/2013