Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- BROOKLINE- IMPROVEMENTS TO COMMONWEALTH AVENUE, FROM ARMORY STREET TO ALCORN STREET
This project will improve a principal arterial roadway by upgrading pavement & drainage conditions, improving facilities for bikes and pedestrians, and widening the MBTA reservation. The upgrades will be consistent with Boston's Commonwealth Avenue Phase 1 project.
Location:
  • City of Boston
  • Town of Brookline
  • Resident Engineer: Mauricio Morales
    Construction Bid Price: $17,617,777.00
    District: District 6

    Contracts (2) Progress
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 90723 -- Construction Contract
    Roadway Reconstruction on a Section of Commonwealth Avenue (Route 20) (Phase 2A). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/16/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/21/2010
    Project Initiation Form PIF Entered 09/21/2010
    Project Initiation Form PRC Submitted 09/21/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 09/21/2010
    Project Status Advertised 09/19/2015
    Project Management
    100% Design 100% Package Received 07/01/2015
    100% Design 100% Package Comments to DE 08/14/2015
    25% Design 25% Package Received 05/24/2011
    25% Design 25% Package Comments to DE 02/29/2012
    25% Design Design Public Hearing 03/28/2012
    75% Design 75% Package Received 07/01/2015
    Final Design PS&E Received 08/20/2015
    Final Design PS&E to FAPRO 09/16/2015