Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOURNE- SANDWICH- RESURFACING OF ROUTE 6 (MID-CAPE HIGHWAY), FROM SAGAMORE BRIDGE TO SANDWICH/BARNSTABLE T.L. INCLUDES 6 BRIDGES
Work on this project includes roadway resurfacing (mill and overlay) of the existing roadway. Drainage improvements, bridge work, safety improvements and associated work will also be included in this contract. The project extends along Route 6 from the South side of the Sagamore Bridge Easterly to the Sandwich/Barnstable town line, a total length of approximately 8.5 miles.
Location:
  • Town of Bourne
  • Town of Sandwich
  • Resident Engineer: Daniel Mastrangelo
    Construction Contract Value: $8,061,701.72
    Construction Bid Price: $5,896,764.00
    Initial Construction Estimate: $5,608,543.00
    District: District 5

    Contracts (2) Progress
    # 60516 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 6 (Mid-Cape Highway) Including 6 Bridges Completed
    # 64301 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/18/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/27/2010
    Project Initiation Form PIF Entered 09/27/2010
    Project Initiation Form PRC Submitted 09/27/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/22/2010
    Project Status Advertised 12/29/2012
    Project Management
    100% Design 100% Package Received 11/05/2012
    100% Design 100% Package Comments to DE 12/20/2012
    25% Design 25% Package Received 05/18/2012
    75% Design 75% Package Received 05/18/2012
    75% Design 75% Package Comments to DE 10/19/2012
    Final Design PS&E Received 12/20/2012
    Final Design PS&E to FAPRO 12/21/2012