| Project Description: |
DISTRICT 3- RESURFACING & RELATED WORK ON I-90, FROM THE I-84 INTERCHANGE (EXIT 9 - MM 78.2) IN STURBRIDGE TO THE WEST STREET BRIDGE (MM 89.0) IN AUBURN
This project consists of micromilling, resurfacing, and guardrail upgrades on I-90 from the I-84 bridge in Sturbridge (mm 78.2) to the West Street bridge in Auburn (mm 89.0) for a distance of 10.8 miles.
|
| Location: | |
| Resident Engineer: | Webster Larkin Sr![]() |
| Construction Contract Value: | $13,902,413.00 |
| Construction Bid Price: | $11,627,837.50 |
| Initial Construction Estimate: | $10,600,000.00 |
| District: | District 3 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||||||||