| Project Description: |
DISTRICT 3- RESURFACING & RELATED WORK ON I-90
This project consists of resurfacing and related work on I-90 from the Oxford/Auburn Town Line (mm 88) to the Auburn/Millbury (mm 93). The work to be done primarily includes resurfacing the mainline, replacing guardrail, replacing concrete median barrier wall, stormwater improvements, and installing signs and pavement markings.
|
| Location: | |
| Resident Engineer: | Webster Larkin Sr![]() |
| Construction Contract Value: | $10,800,000.00 |
| Construction Bid Price: | $8,476,259.83 |
| Initial Construction Estimate: | $7,574,535.40 |
| District: | District 3 |
|