Project Description:
GRAFTON- MILLBURY- RESURFACING AND RELATED WORK ON I-90
This project will micromill and resurface I-90 from the Millbury/Auburn town line (mm 93.1±) to the Grafton/Westborough town line (mm 101.3±). Related work will include guardrail replacement, replacing median guardrail with concrete median barrier, median widening, clearing and grubbing, stormwater improvements, replacing signs, and new pavement markings.
Location:
  • Town of Millbury
  • Construction Begins: Summer 2016
    Resident Engineer: Tracey Coppellotti
    Construction Bid Price: $13,631,159.06
    District: District 3

    Contracts (3) Progress
    # 57238 -- Design -- Services
    Work will consist of providing statewide photogrammetric services on an as needed assignment basis over a period of 60 months. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 93653 -- Construction Contract
    Resurfacing and Related Work along a Section of Interstate 90 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/16/2016
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/01/2010
    Project Initiation Form PIF Entered 10/05/2010
    Project Initiation Form PRC Submitted 10/08/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/22/2010
    Project Status Advertised 03/12/2016
    Project Management
    100% Design 100% Package Received 12/29/2015
    100% Design 100% Package Comments to DE 02/02/2016
    25% Design 25% Package Received 09/10/2015
    25% Design 25% Package Comments to DE 10/01/2015
    75% Design 75% Package Received 09/10/2015
    75% Design 75% Package Comments to DE 10/01/2015
    Final Design PS&E Received 12/29/2015
    Final Design PS&E to FAPRO 02/29/2016