Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
TAUNTON- LAKEVILLE- CABLE BARRIER INSTALLATION ON ROUTE 140
Installation of a median safety barrier between Exits 9 and 12 for a length of 6.4 miles.
Location:
  • Town of Lakeville
  • City of Taunton
  • Resident Engineer: David Ribeiro
    Construction Contract Value: $1,074,510.00
    Construction Bid Price: $858,646.25
    Initial Construction Estimate: $1,050,691.50
    District: District 5

    Contracts (1) Progress
    # 70092 -- Construction Contract
    Cable Barrier Installation on a Section of Route 140. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/21/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/08/2010
    Project Initiation Form PIF Entered 10/08/2010
    Project Initiation Form PRC Submitted 10/08/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/23/2010
    Project Status Advertised 07/23/2011
    Project Management
    100% Design 100% Package Received 07/08/2011
    25% Design 25% Package Received 03/15/2011
    75% Design 75% Package Received 03/21/2011
    75% Design 75% Package Comments to DE 04/14/2011
    Final Design PS&E Received 07/15/2011
    Final Design PS&E to FAPRO 07/15/2011