Project Description: |
TAUNTON- LAKEVILLE- CABLE BARRIER INSTALLATION ON ROUTE 140
Installation of a median safety barrier between Exits 9 and 12 for a length of 6.4 miles.
|
Location: |
|
Resident Engineer: | David Ribeiro |
Construction Contract Value: | $1,074,510.00 |
Construction Bid Price: | $858,646.25 |
Initial Construction Estimate: | $1,050,691.50 |
District: | District 5 |
|
Bridges |
|
|
|
|