Project Description:
ANDOVER- TEWKSBURY- INTERSECTION & SIGNAL IMPROVEMENTS AT DASCOMB ROAD, EAST STREET & SHAWSHEEN STREET
This project will realign the East Street / Dascomb Road and Shawsheen Street legs of the intersection and install a traffic control signal. Exclusive turning lanes will be built.
Location:
  • Town of Andover
  • Town of Tewksbury
  • Resident Engineer: Stephen Doherty
    Construction Contract Value: $1,531,236.00
    Construction Bid Price: $1,354,987.77
    Initial Construction Estimate: $1,458,102.00
    District: District 4

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 81501 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) on a Section of Dascomb Road and East Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/08/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/13/2010
    Project Initiation Form PIF Entered 10/13/2010
    Project Initiation Form PRC Submitted 10/19/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/23/2010
    Project Status Advertised 03/22/2014
    Project Management
    100% Design 100% Package Received 02/07/2013
    100% Design 100% Package Comments to DE 03/24/2013
    25% Design 25% Package Received 04/26/2012
    25% Design Design Public Hearing 01/02/2013
    75% Design 75% Package Received 04/26/2012
    75% Design 75% Package Comments to DE 11/16/2012
    Final Design PS&E Received 09/20/2013
    Final Design PS&E to FAPRO 12/23/2013