Project Description:
BOSTON- YAWKEY WAY EXTENSION
The proposed project consists of construction of a new roadway from Brookline Avenue to Maitland Street and the realignment of Maitland Street. and Overland Street. These improvements will provide a continuous public way, pedestrian accommodations including sidewalks and crosswalks as well as bicycle accommodations including bike lanes where appropriate on the new Yawkey Way Extension and Maitland Street. Also proposed is the construction of a multi-modal path along Yawkey Way Extension to connect the planned future Fenway Station multi-use path to the new Yawkey Station.
Location:
  • City of Boston
  • Resident Engineer: Fritz Dubuisson
    Construction Contract Value: $4,249,073.67
    Construction Bid Price: $3,491,397.93
    Initial Construction Estimate: $3,718,033.00
    District: District 6

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64325 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 76475 -- Construction Contract
    Yawkey Way Roadway Extension and Roadway Reconstruction and Related Work of Maitland and Overland Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/18/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/15/2010
    Project Initiation Form PIF Entered 10/15/2010
    Project Initiation Form PRC Submitted 10/15/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/23/2010
    Project Status Advertised 12/15/2012
    Project Management
    100% Design 100% Package Received 04/06/2012
    100% Design 100% Package Comments to DE 06/12/2012
    25% Design 25% Package Received 04/08/2011
    25% Design 25% Package Comments to DE 05/13/2011
    25% Design Design Public Hearing 05/25/2011
    Final Design PS&E Received 10/19/2012
    Final Design PS&E Received 11/14/2012
    Final Design PS&E to FAPRO 12/12/2012
    Consultant Contract Process Scope to DE 12/01/2010
    Consultant Contract Process NTP Issued 01/19/2011