RUTLAND- BRIDGE REPLACEMENT, R-14-004, INTERVALE ROAD OVER EAST BRANCH OF WARE RIVER
This is a 75’ long three span continuous steel beam bridge with a 28’ wide concrete deck. It carries Intervale Road over East Branch of Ware River. The bridge will be replaced with a single span bridge. The proposed superstructure will consist of galvanized steel beams or concrete bulb tees and 8” concrete deck or with 3” of HWA wearing surface. Abutments will be integral and supported on H-piles. The bridge profile is expected to remain approximately the same.
Location:
  • Town of Rutland
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Carmen Ramirez
    Construction Bid Price: $1,503,614.00
    District: District 3

    Contracts (3) Progress
    # 58994 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 96789 -- Construction Contract
    Bridge Replacement Br. No. R-14-004 (Steel) (Intervale Road) over the East Branch of the Ware River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/22/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/19/2010
    Project Initiation Form PIF Entered 10/19/2010
    Project Initiation Form PRC Submitted 11/15/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/24/2010
    Project Status Advertised 08/06/2016
    Project Management
    100% Design 100% Plans Approved 04/08/2016
    100% Design 100% Plans Complete 04/08/2016
    25% Design 25% Package Received 08/20/2015
    25% Design 25% Package Comments to DE 10/15/2015
    25% Design Design Public Hearing 12/01/2015
    75% Design 75% Package Received 02/12/2016
    75% Design 75% Package Comments to DE 04/05/2016
    75% Design 75% Plans Approved 04/08/2016
    75% Design 75% Plans Complete 04/08/2016
    Final Design PS&E Received 05/06/2016
    Final Design PS&E to Peer Reviewer 05/20/2016
    Final Design Peer Review Comments to DE 06/29/2016
    Final Design PS&E to FAPRO 07/29/2016
    Final Design PS&E Received - Resub 1 07/13/2016
    Consultant Contract Process Scope to DE 07/02/2014
    Consultant Contract Process NTP Issued 07/17/2014
    Consultant Contract Process Workhours Approved 07/08/2014